The development plan offers numerous possible uses by designating it as a mixed area.
Following the development, the area was divided into 3 mixed areas.
M1 mainly describes the former administration building with a usable area of approx. 4,500 sqm
(3 entrance villa) on a plot area of approx. 5,900 sqm. Adjacent to the administration building are former warehouse, workshop and laboratory buildings with a usable area of 3,900 sqm (4 laboratories).
M2 essentially describes the former production building (7 production) built as a closed H with a surface area of approx.16,000 sqm, which has an area of 9,000 sqm distributed over 3 floors.
The building was built in concrete skeleton construction and is therefore flexible in use. Also in this section is a warehouse with a usable area of 384 sqm, which was built as a steel profile sheet with insulation (5 warehouse) and several garages with a total usable area of 800 sqm.
In addition, there is the former boiler house (6 workshops) with almost 800 sqm of floor space.
M3 describes the adjacent parking lot (8 parking lots) and an undeveloped lot (9 vacant lot)